East Broad Top Pictorial 2006

FEBT Rockhill Restoration, Mar 8-13, 2006

These photos are presented in roughly chronological order. Person and vehicle identifications are always in the order from left to right. All photos taken with a Canon Eos RebelXS camera with either a Tamron 28-80mm lens or a Canon 75-300mm lens. Film is Kodak Max 400. All photos in this section copyright 2006 by William Adams.

This was an FEBT Rockhill Restoration work week. The question of week-long sessions is often raised, and this is the second one for the FEBT. The extra time allows timely completion of larger projects, but has not been a draw for volunteers.

Paintshop [2006may8,stone] small - large
A load of stone that will be laid down prior to the concrete.

Paintshop [2006may8,dig1] small - large
Digging the foundation with an excavator.

Paintshop [2006may8,foundation] small - large
The first truck arrives to pour the foundation.

Paintshop [2006may8,conveyor] small - large
A little improvisation to save labor on placing gravel.

Paintshop [2006may8,dig2] small - large
Digging the foundation with an excavator.

Paintshop [2006may8,dig3] small - large
The excavation revealed the concrete conduit containing the steam heating pipe installed for the extant brick paintshop.

Paintshop [2006may8,brick] small - large
A view of the brick foundation of the previous wood paintshop which burned along with the bus garage in 1933.

Paintshop [2006may8,weld] small - large
Welding the far crane rail in place.

Paintshop [2006may8,form1] small - large
The form is built along the edge while the far crane rail is welded in place.

Paintshop [2006may8,form2] small - large
The form is braced to withstand the weight of the concrete.

Paintshop [2006may8,firstpour1] small - large
Ready to start the first pour.

Paintshop [2006may8,firstpour2] small - large
Truck's here! And not 10 seconds after we finished preparations and mistakingly thought we'd get a few minutes rest.

Paintshop [2006may8,firstpour3] small - large
The moment of truth as the concrete flows in.

Paintshop [2006may8,firstpour4] small - large
Spreading concrete while following with a screed to level off the slab.

Paintshop [2006may8,firstpour5] small - large
After two trucks of concrete, the pad is poured out to between the running rails. It will be floated and textured as it sets.

Paintshop [2006may8,morestone] small - large
Spreading stone for the second half of the pad. The form work on the near side is already in place.

Paintshop [2006may8,railing] small - large
The railing is being welded together. It the first project to use the pad.

Paintshop [2006may8,secondpour1] small - large
After several days of delay for rain and concrete availability, the pour for the second half of the slab is begun.

Paintshop [2006may8,secondpour2] small - large
First truck is out, need to go get another load!

Paintshop [2006may8,secondpour3] small - large
A bird's eye view of the slab awaiting the final truckload.

Paintshop [2006may8,secondpour4] small - large
Bullfloating the slab to smooth it.

Paintshop [2006may8,secondpour5] small - large
The slab is covered to permit it to cure slowly. Everyone is tired, but there's cleanup and then another hour or two of unrelated work to do before everyone finally heads home after 8 days.


Back to EBT Pictorial

page by Bill Adams